How an OEM racket project actually runs, from brief to first shipment
The six stages every custom racket programme goes through, what can go wrong at each one, and where the money actually sits.
Most first-time buyers imagine the process as: send a design, get a price, place an order. In practice a racket programme is six stages, and the expensive mistakes almost never happen in the factory — they happen in the brief.
Stage 1 — the brief
Before anything is quoted, four numbers decide most of the outcome:
- Head size (100 in² is the industry’s default; 98 and 105 pull in opposite directions)
- Unstrung weight (a 300 g frame and a 285 g frame are different products, not variants)
- Balance (head-light frames feel faster; head-heavy frames feel heavier through contact)
- Target volume (this single number decides whether tooling is amortised over 300 units or 3,000)
A brief that says “like a Wilson Blade but cheaper” cannot be costed. A brief with the four numbers above can be quoted in a day.
Stage 2 — spec sheet and feasibility
The factory maps the brief onto what its existing moulds can do. If a mould exists in the right head shape, you are buying paint and layup. If not, you are buying a mould — the single largest fixed cost in the project, and one that is wasted if sales volume never justifies it.
Rule of thumb: if target volume is under a few hundred units per year, start from an existing mould and differentiate on layup, weight distribution and finish. A new mould only makes sense when the shape itself is the product.
Stage 3 — prototype
Prototypes are hand-laid. That means the first samples are not production-representative in one specific way: hand layup gives tighter control than a production line, so a prototype often feels slightly better than the shipped product. Ask explicitly how the factory controls layup consistency at volume.
Stage 4 — validation
This is where a serious buyer spends two weeks and a casual buyer skips forward. What to check:
| Check | Why it matters |
|---|---|
| Static weight and balance, measured on a scale, per sample | Catches the difference between “300 g target” and “300 g achieved” |
| Swing weight | Two frames with identical static weight can swing very differently |
| Paint adhesion and edge wear | The most common warranty claim on private-label frames |
| Handle pallet consistency | Grip size drift is felt immediately by players |
| String tension retention over 48 h | Separates frame quality from stringing quality |
Stage 5 — production and QC
Production runs to the approved sample. The important question is not “can you hit the spec” but “what is your tolerance, and what happens to units outside it”. Ask for the AQL level and the sampling plan in writing.
Stage 6 — first shipment
Two things bite here: packaging (a racket in a thin poly bag arrives with paint chips) and documentation (HS code, material declaration, and any destination-specific labelling). Both are cheap to fix before shipping and expensive to fix after.
Key takeaways
- Four numbers — head size, weight, balance, volume — turn a wish into a quotable brief.
- Tooling is the biggest fixed cost; below a few hundred units a year, use an existing mould.
- Prototypes are hand-laid and usually feel better than production. Ask how layup consistency is controlled at volume.
- Write the tolerance and AQL into the PO, not into an email thread.
If you have a spec you are trying to price, the four numbers above are enough to start.